For preliminary sizing, the total depth of a reinforced concrete beam is between 1/15 and 1/10 of its span. A beam spanning 5 m between supports will therefore be about 35 to 50 cm deep, part of which projects below the floor: this is the downstand. These ratios are used to start the project; the final cross-section is set by calculation.
Preliminary sizing orders of magnitude
| Span between supports | Depth L/15 | Depth L/10 |
|---|---|---|
| 3 m | 20 cm | 30 cm |
| 4 m | 27 cm | 40 cm |
| 5 m | 33 cm | 50 cm |
| 6 m | 40 cm | 60 cm |
The width is commonly between 0.4 and 0.7 times the depth. The heavier the load (wall above, column resting on the beam), the closer you get to L/10, or even beyond. A cantilever beam is designed differently and generally requires a much greater depth relative to its length.
RPS rules for beams
The Moroccan seismic code sets minimum dimensions for beams forming part of the bracing system: a width of at least 20 cm, a width-to-depth ratio of at least 0.25, and a width limited relative to that of the supporting column. It also requires longitudinal bars of at least 10 mm and closer stirrups near the supports, in the critical zones.
How to reduce the downstand?
- Add a support (column or wall) to divide the span: this is the most effective solution.
- Widen the beam and reduce its depth (flat beam or beam embedded in the floor), at the cost of more steel and a deflection to be checked.
- Use a solid slab spanning in two directions rather than a single beam.
- Switch to a steel beam or prestressed concrete for very long spans.
- Place the beam as an upstand, above the floor, when the use allows it (terrace, parapet).
Each option has consequences on cost, deflection and seismic behaviour; they are discussed at the preliminary design stage, not on site.
Deflection, often overlooked
A beam that is too thin may resist without breaking but deform excessively: tiles coming loose, cracked partitions, jammed doors and windows. It is often deflection, more than strength, that governs the depth of a long-span beam. If you notice cracks, our article on cracks in a house will help you interpret them.
The role of the engineering firm
The engineering firm balances architectural requirements and structural constraints: it calculates each beam, checks deflection and RPS compliance, and proposes alternatives if a downstand is a problem. Any removal of a column or increase in span during construction must be submitted to it (see opening a load-bearing wall).
Frequently asked questions
What beam depth for a 5 m span?
For preliminary sizing, between L/15 and L/10, i.e. about 35 to 50 cm for 5 m. The final depth depends on the loads and deflection and must be calculated.
What is the minimum beam width under the RPS?
The Moroccan seismic code requires a width of at least 20 cm and a width-to-depth ratio of at least 0.25 for beams.
Can the downstand of a beam be eliminated?
It can be reduced with a wider flat beam, an additional support or a solid slab, but each solution must be calculated by the engineer.