Le Noyer A, No. 23, 2nd floor, Ibn Sina, Guéliz, Marrakech +212 6 61 05 74 55 · +212 6 20 89 76 60 · sigma.icc@gmail.com
Home / Advice / Buying and inspection / Order of works

Renovating an old house: where to start and in what order

Redoing the kitchen before the roof means risking having to start all over again. Here is the logical order of a renovation, from assessment to finishes.

Published 16 November 2026 · 3 min read · SIGMA ICC, engineering consultancy

A renovation always starts with a full assessment, then follows the order "from heavy to fine": structure, roof and waterproofing, damp treatment, services (electrics, plumbing, air conditioning), windows and doors, insulation, then finishes. Each stage protects the next; reversing the order means breaking what has just been redone.

Step 1: the assessment

Before asking for quotes, have a technical survey carried out: structure, damp, electrics, plumbing, drainage. It is used to prioritise the work, avoid surprises during the works and obtain comparable quotes. If you have not bought the house yet, see our pre-purchase checklist.

The order of works

  1. Permits: depending on the type of work (structure, façade, extension, additional storey), authorisation is required. See our article on permits for renovation work.
  2. Structure: strengthening foundations, repairing cracks, reinforcing or replacing floors, openings in load-bearing walls. Anything that affects the structure must be calculated by an engineer.
  3. Roof and waterproofing: a house must be watertight before investing in the interior.
  4. Damp: treating rising damp, drainage, ventilation. The walls must be able to dry out before plastering.
  5. Concealed services: electrics, plumbing, waste pipes, air-conditioning ducts, low-voltage systems. This is the time to plan them all, even those you will install later.
  6. External windows and doors: preferably double-glazed for the Marrakech climate.
  7. Insulation: the flat roof first, then exposed walls.
  8. Plaster, floors and finishes: last, once the wall chases have been filled.

Costly mistakes

MistakeConsequence
Repainting before treating the dampBlistering and efflorescence within a few months
Laying tiles before redoing the plumbingTiles to break to replace a pipe
Opening a wall without a studyCracks, or even serious structural damage
Not planning air-conditioning ductsVisible trunking or work to be redone
Keeping the old consumer unitNew installation poorly protected

Budget and phasing

If the budget does not allow everything at once, first carry out what concerns safety and durability (structure, waterproofing, electrics) and postpone the decoration. Allow a contingency reserve, as opening up walls and floors always reveals surprises in old buildings. Also plan around the season: in Marrakech, waterproofing and plastering work do not cope well with the intense summer heat, and the roof must be dealt with before the winter rains.

The role of the engineering firm

The engineering firm turns the assessment into a works programme: calculating reinforcements, electrical and plumbing diagrams, sizing the air conditioning, a specification for consulting contractors, then site supervision. SIGMA ICC supports the renovation of houses and riads in Marrakech, from the initial survey to final acceptance.

Frequently asked questions

Where should you start when renovating a house?

With a full technical assessment, then structural, roofing and waterproofing work, before the services, windows and doors, insulation and finishes.

Do you need a permit to renovate a house in Morocco?

It depends on the work: work affecting the structure, façades or volumes requires authorisation; light interior work generally does not. Check with the municipality.

Can you renovate in stages?

Yes, by dealing first with safety and durability (structure, waterproofing, electrics) and postponing the finishes, provided you plan all the concealed services from the outset.

A project in the pipeline?

SIGMA ICC designs reinforced concrete, electrical, plumbing and HVAC systems and supervises sites for villas, riads, hotels and shops.

Sources : ReaConsult, acheter un bien ancien et estimer les vrais travaux.

Can we help you?

Click to call, or write to us: we answer 7 days a week for emergencies.

Chat on WhatsApp