Underpinning means strengthening, widening or deepening the foundations of an existing building without demolishing it. It is used when the foundations are settling, when you want to add a storey or dig a basement, or when neighbouring works destabilise the soil. The main techniques are concrete pads cast in alternate bays, micropiles and soil injection.
Situations that require it
- Differential settlement: stepped or diagonal cracks, sticking doors, sloping floors.
- Vertical extension: the original foundations are no longer enough to carry one or two more storeys (see adding a storey).
- Digging a basement or a swimming pool close to existing walls.
- Foundations damaged by water leaks, washed-out soil or neighbouring excavation.
The techniques
| Technique | Principle | When to use |
|---|---|---|
| Alternate-bay pads | Digging under the foundation in short, non-adjacent sections and pouring concrete down to the good soil | Good soil accessible at shallow depth |
| Micropiles | Small-diameter piles (generally less than 25 to 30 cm) drilled and reinforced, connected to the foundation by a beam or pile caps | Deep good soil, restricted access, heavy loads |
| Soil injection | Grout or resin injected to consolidate the soil under the foundation | Loose or decompressed soils, depending on the diagnosis |
| Footing widening | Existing footing widened and connected by grouted-in bars | Increased loads on reasonable soil |
Why work in alternate bays
Digging under a whole wall at once would leave it unsupported. Work is therefore done in short sections, skipping one section in two or three: sections 1, 3 and 5 are underpinned first, then, once the concrete has hardened, sections 2, 4 and 6. The length of the sections and the sequence are set by the engineer according to the condition of the wall and the soil. Dry-packing, i.e. tightly filling the gap between the old foundation and the new concrete, is essential for the load to be genuinely transferred.
Essential precautions
- Preliminary diagnosis: soil investigation, trial pits at the foot of the existing foundations, crack survey.
- Propping of floors if necessary and crack monitoring (tell-tales, levelling marks).
- Treating the cause: repair the leak or the pipe that washed out the soil, otherwise the problem will come back.
- An experienced contractor: this is not ordinary masonry work.
- Informing neighbours where walls are shared: neighbouring foundations may be affected, and a record of the condition of their walls before work is a sensible precaution.
The role of the engineering firm
The engineering firm analyses the cause of the damage, chooses the technique with the geotechnical engineer, calculates the new supports and defines the sequencing. It then supervises the work to adapt the sequencing to the soil actually encountered. If cracks are worrying you, our article on cracks in a house helps assess how serious they are.
Frequently asked questions
What is underpinning?
It is the strengthening, widening or deepening of the foundations of an existing building, using concrete pads, micropiles or injection, without demolishing the structure.
Why dig in alternate bays?
So that a wall is never left unsupported: short, non-adjacent sections are underpinned first, then the intermediate sections once the concrete has hardened.
When should micropiles be used?
When the good soil is deep, access is restricted or the loads are heavy; they are small-diameter piles that are drilled and reinforced.
A project in the pipeline?
SIGMA ICC designs reinforced concrete, electrical, plumbing and HVAC systems and supervises sites for villas, riads, hotels and shops.
Sources : Cerema (SETRA-LCPC), les micropieux, guide technique · Terrasol, reprise en sous-œuvre de bâtiments sensibles.