It all depends on the nature of the works. Under Law 12-90 on urban planning, a building permit is required for a new building and for any modification of an existing building affecting what was authorised: floor area, volume, height, façades, structure or use. Purely interior and maintenance works generally involve a lighter procedure with the municipality, or none at all, depending on local rules. If in doubt, ask the municipality's urban planning department or check via Rokhas before you start.
Which level of authorisation for which works
| Works | Usual procedure |
|---|---|
| Painting, tiling, kitchen, bathroom without structural changes | Usually no planning authorisation, to be checked locally |
| Like-for-like refurbishment of façade, renders or roof | Authorisation from the municipality (often called a repair authorisation) |
| Opening or removing a load-bearing wall | Structural study mandatory; authorisation depending on the impact |
| New opening in the façade, enclosing a balcony or terrace | Building permit (change in appearance or floor area) |
| Adding a storey, extension, change of use | Building permit with an architect |
Riads and the medina
The medina of Marrakech is a World Heritage Site and is subject to specific rules: materials, heights, street openings, colours. Works there, even modest ones, are more tightly regulated and the opinions of the competent departments may be required. Before buying or renovating a riad, consult the urban agency and the municipality. See buying a riad to renovate in Marrakech.
The risks of undeclared works
- Site stoppage and an infringement report under Law 66-12 on the control and punishment of urban planning infringements.
- Fines and, in serious cases, demolition of the unauthorised parts.
- Problems on resale: discrepancy between the building and the permit, difficulty obtaining a certificate of conformity.
- Structural risk: a load-bearing wall removed without calculation can cause cracks or collapse.
The recommended approach
- Describe the planned works precisely.
- Have a BET check anything affecting the structure (walls, slabs, beams).
- Ask the municipality which authorisation is required and submit the application.
- Keep the authorisation on site.
Co-ownership and neighbours. In an apartment building, the administrative authorisation is not enough: works affecting the common parts, the structure or the external appearance also require the agreement of the co-owners, according to the building's regulations. Warn your neighbours about disturbances (noise, dust, access) and plan reasonable working hours. If the works risk affecting a party wall or an old neighbouring building, a pre-works condition survey avoids many disputes.
The role of the engineering consultancy
The BET carries out the survey of the existing building, the calculation note and the strengthening drawings when you touch the structure, documents generally required in the application. See also opening or removing a load-bearing wall.
Frequently asked questions
Do you need a permit to redo a bathroom?
Generally not if there is no change to the structure, façade or floor area; however, check your municipality's rules, which are stricter in the medina.
Which renovation works require a building permit?
Those that change the floor area, volume, height, façades, structure or use of the building: adding a storey, extension, new opening, enclosing a terrace.
What are the risks of renovating without authorisation?
A site stoppage, an infringement report and fines under Law 66-12, or even demolition of the unauthorised parts, as well as difficulties on resale.
A project in the pipeline?
SIGMA ICC designs reinforced concrete, electrical, plumbing and HVAC systems and supervises sites for villas, riads, hotels and shops.
Sources : Médias24, obtenir un permis de construire · Médias24, contrôle des infractions d'urbanisme.