Contract with your construction company: the essential clauses

Most site disputes stem from a contract that is too short. Here are the clauses to insist on before entrusting the construction of your house to a contractor.

Published 16 November 2026 · 3 min read · SIGMA ICC, engineering consultancy

A solid construction contract fits into a few pages, but it must answer four questions without ambiguity: what (the exact content of the works), how much (the price and its terms), when (the deadline and penalties) and what happens if (poor workmanship, delays, disputes). A signed quote is not enough: it rarely describes the expected quality.

The essential clauses

ClauseWhat it must specify
Scope and contract documentsList of drawings (architect, BET), CPS, bill of prices, order of precedence between documents
PriceOverall lump sum or measured unit prices, VAT, possible price revision
Payment schedulePayments tied to verified stages (foundations, structural work, weathertight…), not to dates
DeadlineStart date, duration, accepted grounds for extension
Delay penaltiesAmount per day, cap
Retention moneyPercentage withheld from each payment, conditions for release
InsuranceTRC and decennial civil liability certificates to be provided before work starts
AcceptanceProcedure for provisional acceptance, snag items, final acceptance
DisputesAmicable settlement attempt, expert appraisal, competent court

Lump sum or measured price?

  • Lump sum: a fixed overall price for a well-defined building. It protects the budget, provided the drawings and CPS are complete; otherwise every omission becomes an “extra”.
  • Measured (unit prices): you pay for the quantities actually carried out. More flexible, but the final cost is only known at the end and each progress statement must be checked.

In both cases, insist that any additional work be covered by a written, priced amendment before it is carried out.

Common pitfalls

  1. Large down payment at the start: limit it to what covers site set-up and the first supplies.
  2. Undetailed “supply and installation”: specify brands, ranges, thicknesses, cable cross-sections, concrete classes.
  3. Hidden subcontracting: provide that it must be declared and approved. Reminder: decennial liability under Article 769 of the DOC targets the parties contracted directly by the client.
  4. No construction drawings: without the BET's drawings, the contractor “does it the usual way”, which does not necessarily comply with RPS 2011.

Before signing

Check the company's legal identity (trade register, tax identification number), its recent references and, if possible, visit one of its ongoing sites. Have the contract reviewed by your architect or BET: they spot discreet exclusions (earthworks, spoil removal, utility connections, cleaning) that later come back as extras. Finally, attach a provisional stage-by-stage schedule to the contract: it will serve as the reference for applying delay penalties.

The role of the engineering consultancy

A contract is only as good as the technical documents that accompany it. The BET produces the construction drawings, the special technical specifications and the bill of quantities that make it possible to compare bids on an identical basis, then checks the progress statements before payment. See also the decennial guarantee in Morocco.

Frequently asked questions

Is a signed quote a contract?

It binds the parties on the price, but rarely describes the quality, deadline, penalties and acceptance; a contract accompanied by drawings and a CPS is much more protective.

How should a construction company be paid?

Through a payment schedule tied to stages verified on site (foundations, walls, slabs, weathertight), with retention money withheld from each payment.

Should you require the contractor's insurance?

Yes: ask for the insurance certificates, in particular decennial civil liability, before work starts.

A project in the pipeline?

SIGMA ICC designs reinforced concrete, electrical, plumbing and HVAC systems and supervises sites for villas, riads, hotels and shops.

Can we help you?

Click to call, or write to us: we answer 7 days a week for emergencies.

Chat on WhatsApp