Electrical work is the trade where a design error is least visible at handover and most expensive afterwards: repeated tripping, overheating, no earthing, too few sockets. In building electrical studies, the most widely used technical reference remains the French standard NF C 15-100, itself derived from the international standard IEC 60364.
What is NF C 15-100?
It is the standard that sets the rules for the design, installation and inspection of low-voltage electrical installations in buildings. It covers the internal installation, downstream of the main incoming circuit breaker; the service connection itself falls under another standard, NF C 14-100. In Morocco, it is commonly cited in specifications and serves as the basis for the work of engineering firms and inspection bodies; your special technical specifications (CPS) and the distributor (ONEE, municipal utility or concession holder depending on the city) may add their own requirements.
What changed with the 2024 edition
A new edition was published by AFNOR at the end of August 2024. The single 2002 document and its amendments have given way to a series of about twenty standards (NF C 15-100-1, -7-701, -10, etc.): one part for general requirements, parts dedicated to special locations (bathrooms, swimming pools, car parks, photovoltaic installations, electric vehicle charging) and parts specific to dwellings. According to the FFB, the sizing rules have been completely revised and additional protection strengthened.
Key points for a villa
| Topic | What to check |
|---|---|
| Earthing | Earth electrode measured and connected to all circuits; equipotential bonding in bathrooms. |
| Residual current protection | 30 mA residual current devices at the head of all circuits, distributed to limit total power cuts. |
| Distribution board | One circuit per heavy load (oven, hob, air conditioners, water heater), spare space for future changes, clear labelling. |
| Bathrooms | Safety zones around the bath and shower: no socket or unsuitable appliance near the water. |
| Swimming pool | Specific rules for equipment, underwater lighting and equipotential bonding; ventilated plant room. |
| Air conditioning | Realistic power balance: in summer in Marrakech, air conditioning weighs heavily on the subscribed power and cable sizes. |
| Low-current systems | Technical riser, star-topology IT network, RJ45 sockets in the main rooms, provision for fibre. |
Why go through an electrical study
An experienced electrician knows how to wire; it is not their job to produce the power balance for the whole villa, choose the subscribed power, calculate voltage drops over long distances (garden, pool house, gate) or coordinate the protective devices. The engineering firm's power and low-current (CFO/CFA) study sets these choices out on plans and single-line diagrams, before any chases are cut. The inspection body can then check on a clear basis.
Plan for future upgrades now
Photovoltaic panels, charging point, home automation: these items now have their own dedicated parts in the standard. Planning for them at the design stage (conduits, space in the board, power) costs little; adding them later costs a lot.
A project in the pipeline?
SIGMA ICC designs reinforced concrete, electrical, plumbing and HVAC systems and supervises sites for villas, riads, hotels and shops.