Main equipotential bonding (LEP) connects all the metal pipes and structures entering the building to the main earthing terminal: water supply, gas, heating, metal ducts, accessible structural elements. Its purpose is to prevent a dangerous voltage difference from appearing between two metal parts that can be touched at the same time, for example a tap and the casing of a faulty appliance.
What must be connected
- Metal water pipes where they enter the building (after the meter).
- The gas pipe if it is metal (mains network or pipework from a cylinder store).
- Metal heating and hot water pipes.
- Accessible metal structural elements and metal ducts or conduits.
- In an apartment building: the concrete reinforcement where accessible, metal risers, ventilation ducts.
With PEX, multilayer or PPR pipework, very common today, the LEP mainly concerns the metal sections (copper or galvanised steel water inlet, fittings and manifolds).
Conductor cross-sections
| Conductor | Usual cross-section (copper) |
|---|---|
| Main equipotential bonding | Half the cross-section of the largest protective conductor in the installation, with a minimum of 6 mm² and not exceeding 25 mm² |
| Earthing conductor (earth electrode to test link) | 16 mm² insulated and protected, 25 mm² bare |
| Circuit protective conductors | Same cross-section as the circuit's live conductors |
Example: with a 16 mm² main protective conductor, the LEP is made in 10 mm². For a standard house, 6 mm² is the most common value. The conductor is green-yellow, attached with earthing clamps suited to each pipe.
How to install it
- Provide a main earthing terminal (or bar) near the board or in the service duct.
- Fit a clamp on each metal pipe, as close as possible to where it enters the building.
- Connect each clamp to the main terminal with a green-yellow conductor of suitable cross-section, without cutting it along the way.
- Label the connections and leave them accessible for inspection.
LEP and LES: do not confuse them
The LEP is general and starts from the main earthing terminal. Supplementary equipotential bonding (LES) is local: it mainly concerns the bathroom, see LES in the bathroom. Both complement the earth electrode described in earthing a house.
The engineering firm shows the LEP on the electrical and plumbing drawings, which allows it to be coordinated between the two trades. It is a point the inspection body systematically checks before the installation is energised. In renovation work, the absence of an LEP is one of the most common defects in older houses: installing one is inexpensive and significantly improves safety, provided the earth electrode itself is sound.
Frequently asked questions
What cross-section for main equipotential bonding?
The LEP is half the cross-section of the largest protective conductor in the installation, with a minimum of 6 mm² and a maximum of 25 mm² in copper.
Do PEX pipes need to be connected to earth?
No, synthetic pipes are not conductive; equipotential bonding concerns metal parts, such as a copper or steel water inlet.
Where is the main equipotential bonding connected?
It starts from the main earthing terminal, near the board or in the service duct, to which the earthing conductor and the protective conductors are also connected.
A project in the pipeline?
SIGMA ICC designs reinforced concrete, electrical, plumbing and HVAC systems and supervises sites for villas, riads, hotels and shops.
Sources : IZI by EDF, liaison équipotentielle : installation et obligation · Futura, définition de la liaison équipotentielle.