For a new house, the best earth electrode is a foundation earth loop: a bare copper cable of at least 25 mm² laid at the bottom of the foundation trenches, around the entire perimeter of the building, before the concrete is poured. It is connected to the board by an earthing conductor (16 mm² copper if insulated and protected, 25 mm² if bare). In renovation work, earth rods driven into the ground are used. The resistance obtained must be measured and remain compatible with the residual current devices.
Earth electrode solutions
| Solution | When | Key points |
|---|---|---|
| Foundation earth loop | New construction, when the foundations are laid | Bare copper 25 mm² minimum, in contact with the soil, under the blinding concrete or at the bottom of the trench, both ends accessible for testing |
| Earth rods | Renovation, supplement | Vertical rod, generally 1.5 to 2 m long; several spaced rods connected together if the resistance is too high |
| Ring or conductor in a trench | Rocky ground, extension | Cable buried in a dedicated trench around the building |
What resistance value should you aim for?
The protection rule is that the touch voltage in the event of a fault must remain below 50 V. The maximum allowable value therefore depends on the sensitivity of the residual current device at the head of the installation: with a 500 mA device, you get 100 Ω, the value often cited as the limit. With more sensitive residual current devices, the theoretical limit is higher, but good practice is to aim for a much lower value, a few tens of ohms. A well-executed foundation earth loop generally gives low values.
In Marrakech, soils that are dry and stony in summer can push up the resistance of earth rods. Measure during the dry season and plan for several rods if necessary.
From the ground to the sockets
- The earth electrode (loop or rods).
- The earthing conductor up to the test link (removable, to measure the resistance).
- The main earthing terminal of the board, from which the green-yellow protective conductors of each circuit run.
- The main equipotential bonding, which connects metal pipework and structures, see the LEP.
The earthing system (generally TT for dwellings connected to the low-voltage network) must be confirmed with the distributor (Radeema in Marrakech, ONEE or another utility depending on the city).
Coordinating with the structural work
The foundation earth loop must be laid by the electrician or the mason at the right time: once the concrete is poured, it is too late. The engineering firm includes it in the drawings and the specifications (CPS), and checks its installation during site visits, before pouring. A resistance measurement is taken at handover. In a building, the loop is supplemented by connections to the reinforcement and the earth risers. See also the role of the engineering firm.
Frequently asked questions
What cross-section for a foundation earth loop?
The foundation earth loop is made of bare copper of at least 25 mm², laid in contact with the soil at the bottom of the foundations.
What earth resistance should be achieved?
With a 500 mA residual current device at the head of the installation, 100 Ω is the limit often cited; in practice the aim is much lower, a few tens of ohms at most.
Can an earth electrode be installed after construction?
Yes, with one or more earth rods connected together; the foundation earth loop, which performs better, can only be laid when the foundations are built.
A project in the pipeline?
SIGMA ICC designs reinforced concrete, electrical, plumbing and HVAC systems and supervises sites for villas, riads, hotels and shops.
Sources : IZI by EDF, réaliser une prise de terre en fond de fouille · IZI by EDF, mise à la terre : normes et méthode.