Acceptance of works is the moment when the client accepts the building, with or without reservations (snag items). In most contracts in Morocco it takes place in two stages: a provisional acceptance at the end of the works, then a final acceptance at the end of the guarantee period, once all snag items have been cleared. It must always be recorded in a written, dated and signed report.
The two acceptances
| Stage | When | Effect |
|---|---|---|
| Provisional acceptance | End of the works | Transfer of custody of the building, start of the guarantee period, list of snag items |
| Clearing of snag items | Deadline set in the report | The contractor makes corrections, the client checks them |
| Final acceptance | End of the guarantee period set in the contract | Release of the retention money |
In public contracts, the general administrative conditions for works (CCAG-T) govern these stages; unless the CPS states otherwise, the guarantee period corresponds to the period between provisional and final acceptance. In a private contract, everything depends on what you have written: hence the value of a well-drafted contract.
Preparing the acceptance visit
- Carry out the visit with the architect and the BET, in daylight, with the networks in service (water, electricity, air conditioning).
- Have the drawings, the CPS and the approved samples to hand.
- Go through room by room: floors, walls, ceilings, joinery, hardware, sanitary fittings, sockets, electrical panel, roof terrace.
- Test: open every tap and every window, trip every residual current device, fill a shower to check drainage.
- Photograph each snag item and number it.
Writing snag items properly
- Precise: “1 m crack on the north wall of bedroom 2”, not “finishes to be redone”.
- Located on a drawing if possible.
- Dated, with a deadline for clearing (for example 30 days).
- Comprehensive: anything visible and not listed is deemed accepted.
Retention money
Most contracts provide for a retention on each progress payment, released at final acceptance or replaced by a bank guarantee. Its rate is set by the contract; it is your main lever for getting snag items cleared. Do not release it until the snag items have been cleared and recorded in writing.
Refusing acceptance. If the building has serious defects (significant infiltrations, dangerous electrical installation, obviously unfinished works), you can refuse to accept it rather than piling up snag items. State the reasons for refusal in writing and set a new visit date. On the other hand, avoid moving in or using the building without a report: taking possession without reservations may be interpreted as tacit acceptance. In the event of a persistent disagreement, a joint inspection report or one drawn up by an expert fixes the situation.
The role of the engineering consultancy
The BET checks technical points that an untrained eye cannot see: network tests, earth measurements, commissioning of air conditioning, compliance of electrical panels, roof terrace slopes. SIGMA ICC writes precise snag items and follows up their clearing. For a home bought off-plan, see also acceptance of a VEFA (off-plan) apartment.
Frequently asked questions
What is the difference between provisional and final acceptance?
Provisional acceptance records the end of the works and lists the snag items; final acceptance takes place at the end of the guarantee period, once the snag items have been cleared, and releases the retention money.
What happens if I do not note a visible defect at acceptance?
An apparent defect not listed is in principle considered accepted; it becomes very difficult to have it put right afterwards.
Is a written report required?
Yes, always: a dated and signed report sets the starting point of the guarantees and the list of snag items to be cleared.